Yogi Government To Restart Construction Work

Publish On: 22 Apr, 2020 11:19 AM | Updated   |   Shivalik  

The Yogi government has started taking steps towards restarting the development work, which was disrupted due to the nationwide lockdown to contain the coronavirus spread. The govt is preparing to start the stalled construction of the expressways amid all the COVID-19 precautions.

Uttar Pradesh Expressways Industrial Development Authority Chief military officer Avnish Kumar Awasthi said that apart from the town of Lucknow, offices of the contractor, project implementation unit(PIU) are opened.

The total number of labourers engaged in the construction of the Purvanchal Expressway is 10,000, out of which currently 4,835 labourers are present in eight packages.

Awasthi said that each one of the contractors is instructed to make sure the checkup from the labourers and social distancing between them. Some 42 per cent of the physical work was completed before the lockdown.

The offices of the contractor, PIU and authority engineer also are open in all the districts related to the Bundelkhand Expressway project. Out of the total 6,000 workers engaged in the construction of this project, 2,150 are present at the construction sites through which work is to be done.

Meanwhile, construction work has been started in the Gorakhpur Link Expressway Package-1 (Gorakhpur and Santakbirnagar). A total of 488 labourers are present on the spot for the construction of this expressway. Construction work has started in three out of six packages of the project.